Software Engineering MCQs for job test and interview preparation, especially for fresh graduates, students, and candidates appearing in competitive exams. These multiple-choice questions cover a wide range of topics, including the fundamentals of software engineering, its various types, advanced concepts, software design, development processes, testing methods, software evolution, and security aspects.

Which of the following risk is the failure of a purchased component to perform as expected ?
A Product risk
B Project risk
C Business risk
D Programming risk
Correct Answer: Product risk
Which of the following term is best defined by the statement:”the degree of uncertainty that the product will meet its requirements and be fit for its intended use.”?
A Performance risk
B Cost risk
C Support risk
D Schedule risk
Correct Answer: Performance risk
Which of the following term is best defined by the statement: “There will be a change of organizational management with different priorities.”?
A Staff turnover
B Technology change
C Management change
D Product competition
Correct Answer: Management change
Which risks are associated with constraints imposed by management or the marketplace ?
A Business impact risks
B Process definition risks
C Product size risks
D Development environment risks
Correct Answer: Business impact risks
Which of the following is a systematic attempt to specify threats to the project plan ?
A Risk identification
B Performance risk
C Support risk
D Risk projection
Correct Answer: Risk projection
What threatens the quality and timeliness of the software to be produced ?
A Known risks
B Business risks
C Project risks
D Technical risks
Correct Answer: Technical risks
Which of the following is not a business risk ?
A building an excellent product or system that no one really wants
B losing the support of senior management due to a change in focus or change in people
C lack of documented requirements or software scope
D losing budgetary or personnel commitment
Correct Answer: lack of documented requirements or software scope
Which risks are associated with the overall size of the software to be built or modified ?
A Business impact risks
B Process definition risks
C Product size risks
D Development environment risks
Correct Answer: Product size risks
What threatens the viability of the software to be built ?
A Known risks
B Business risks
C Project risks
D Technical risks
Correct Answer: Business risks
What is the product of the probability of incurring a loss due to the risk and the potential magnitude of that loss ?
A Risk exposure
B Risk prioritization
C Risk analysis
D All of the mentioned
Correct Answer: Risk exposure