Management Sciences focuses on the planning, organizing, leading, and controlling of resources to achieve organizational goals.This subject is highly important for competitive exams, academic study, and professional careers in the business and public sectors.

If an actual input price is $70 and the budgeted input price is $40, then the price variance will be ____________?
A $120
B $50
C $110
D $30
Correct Answer: $30
The process of assigning the direct or indirect cost to any cost object is known as ____________?
A cost assignment
B cost expectation
C event assignment
D probability assignment
Correct Answer: cost assignment
An actual cost is subtracted from flexible budget cost to calculate ____________?
A positive cost variance
B negative cost variance
C flexible budget variance
D flexible cost variance
Correct Answer: flexible budget variance
An approach which yields the benefits of normal costing and the actual manufacturing overhead is classified as ____________?
A unadjusted allocation rate approach
B adjusted budget rate approach
C unadjusted budget rate approach
D adjusted allocation rate approach
Correct Answer: adjusted allocation rate approach
If the budgeted price of input is $50, actual quantity of input is 150 units and the allowed budgeted quantity of input is 60 units then efficiency variance will be __________?
A $4,500
B $3,500
C $2,500
D $1,500
Correct Answer: $4,500
The total indirect cost in the pool by an actual quantity of cost allocation base, is used to calculate ____________?
A actual manufacturing overhead rate
B manufacturing overhead costs
C overhead rate
D direct rate
Correct Answer: actual manufacturing overhead rate
The difference between actual quantity use and input quantity for output is multiplied with budgeted price to calculate ___________?
A efficiency deviation
B efficiency variance
C budgeted variance
D usage variance
Correct Answer: efficiency variance
An under allocated indirect cost is also called ____________?
A under applied indirect cost
B under absorbed indirect cost
C absorbed indirect cost
D both a and b
Correct Answer: both a and b
The budgeted input quantity is added in to efficiency variance to calculate _____________?
A actual input quantity
B actual output quantity
C actual input price
D actual output price
Correct Answer: actual input quantity
If the budgeted annual indirect cost is $60000, budgeted annual quantity of cost allocation base is $3600, then budgeted indirect cost rate will be __________?
A 15.67 per piece
B 16.67 per piece
C 14.67 per piece
D 13.67 per piece
Correct Answer: 16.67 per piece