M C Q s D r i v e

Software Engineering Mcqs 840 MCQs [All-Courses]

thumb

Software Engineering MCQs for job test and interview preparation, especially for fresh graduates, students, and candidates appearing in competitive exams. These multiple-choice questions cover a wide range of topics, including the fundamentals of software engineering, its various types, advanced concepts, software design, development processes, testing methods, software evolution, and security aspects.

Which of the following costs is not part of the total effort cost ?
A Costs of networking and communications
B Costs of providing heating and lighting office space
C Costs of lunch time food
D Costs of support staff
Correct Answer: Costs of lunch time food
A _______________ is developed using historical cost information that relates some software metric to the project cost ?
A Algorithmic cost modelling
B Expert judgement
C Estimation by analogy
D Parkinson’s Law
Correct Answer: Algorithmic cost modelling
A number of independent investigators have developed a team-oriented approach to requirements gathering that can be applied to establish the scope of a project called ?
A JAD
B CLASS
C FAST
D None of the mentioned
Correct Answer: FAST
CLSS stands for_____________________?
A conveyor line sorting system
B conveyor line sorting software
C conveyor line sorting speed
D conveyor line sorting specification
Correct Answer: conveyor line sorting system
The environment that supports the software project is called_______________________?
A CLSS
B SEE
C FAST
D CBSE
Correct Answer: SEE
What is related to the overall functionality of the delivered software ?
A Function-related metrics
B Product-related metrics
C Size-related metrics
D None of the mentioned
Correct Answer: Function-related metrics
Which of the following is not achieved by an automated estimation tools ?
A Predicting staffing levels
B Predicting software cost
C Predicting software schedules
D Predicting clients demands
Correct Answer: Predicting clients demands
Which of the following are parameters involved in computing the total cost of a software development project ?
A Hardware and software costs
B Effort costs
C Travel and training costs
D All of the mentioned
Correct Answer: All of the mentioned
What can be used to complement decomposition techniques and offer a potentially valuable estimation approach in their own right ?
A Automated estimation tools
B Empirical estimation models
C Decomposition techniques
D Both Automated estimation tools and Empirical estimation models
Correct Answer: Empirical estimation models
Which of the following is not an option to achieve reliable cost and effort estimate ?
A Base estimates on similar projects that have already been completed
B Use one or more empirical models for software cost and effort estimation
C Use relatively simple decomposition techniques to generate project cost and effort estimates
D The ability to translate the size estimate into human effort, calendar time, and dollars
Correct Answer: The ability to translate the size estimate into human effort, calendar time, and dollars