M C Q s D r i v e

Mechanical Engineering Mcqs 1919 MCQs [All-Courses]

thumb

Mechanical Engineering MCQs prepared for job test and interview preparation, especially for fresh graduates, students, and candidates appearing in competitive exams. These multiple-choice questions cover key topics such as Machine Design, Theory of Machines, Hydraulic Machines, and other important mechanical engineering concepts.

Critical path moves along the activities having total float of_____________________?
A positive value
B negative value
C zero value
D same value
Correct Answer: zero value
The technique for establishing and maintaining priorities among the various jobs of any project is known as___________________?
A event flow scheduling technique
B critical ratio scheduling
C slotting technique for scheduling
D short interval scheduling
Correct Answer: critical ratio scheduling
PERT analysis is based on____________________?
A optimistic time
B pessimistic time
C most likely time
D all of the above
Correct Answer: all of the above
O on a PERT/CPM chart represents____________________?
A an ordinary event
B a significant event representing some mile-stone
C an event to be transferred to other network chart
D dangling event
Correct Answer: an ordinary event
Criticalpath on PERT/CPM chart is obtained by joining the events having____________________?
A maximum slack
B minimum slack
C average slack
D no slack
Correct Answer: minimum slack
The assumption in PERT is__________________?
A a project will always be behind schedule, if left uncorrected
B cost of project will always be more than the estimated cost, if no timely corrections are taken
C a project can be subdivided into a set of predictable, independent activities
D activities are fixed and can’t be changed ,
Correct Answer: a project can be subdivided into a set of predictable, independent activities
Pessimistic time is___________________?
A the maximum time which an activity might require
B the average time required for a job
C the most probable time considering all conditions
D the minimum time in which an activity can possibly be accomplished
Correct Answer: the maximum time which an activity might require
In a PERT chart___________________?
A all activities should be numbered
B only important activities should be numbered
C only critical activities are numbered
D only selected activities are numbered
Correct Answer: all activities should be numbered
In PERT analysis, critical path is obtained by joining events having___________________?
A +ve slack
B -ve slack
C zero sldck
D dummy activities
Correct Answer: zero sldck
Positive slack on a PERT indicates that project is________________?
A ahead of schedule
B beyond schedule
C as per schedule
D on critical path
Correct Answer: ahead of schedule